As of November 19, 2014, Vanderbilt is coal free! Vanderbilt University currently has an on-campus co-generation, natural gas-fueled power plant which produces 23% of our electricity and 100% of our steam, servicing 12 million square feet of building space. This steam is then used for 90% of campus heating, sterilization, and 40% of campus cooling. This cogeneration process is quite efficient: heat, which would otherwise be a wasted byproduct of electricity and steam generation, is used to produce more steam and hot water. The remaining 77% of electricity consumed at Vanderbilt is purchased directly from Nashville Electric Service from Tennessee Valley Authority (TVA).

The plant is now fueled by 100% natural gas. The conversion of the plant replaced the coal-fired boilers with natural gas boilers, retaining the same power generation capacity. The iconic smokestack, silo, and other coal infrastructure were demolished in the Spring of 2015 as part of a broader renovation to modernize the plant.

  • Our Team

    The Energy Production & Utilities department is overseen by the Plant Manager, John Williams. The department is comprised of a Cogeneration Plant Supervisor, Cogeneration Operator, Power Distribution Specialists, and Welder/Pipefitter. 

  • Investing in Efficient Energy Options

    Investing in the Future 

    The university will explore and implement renewable energy options to produce more highly efficient energy for the university and store excess for resiliency and reliability: 

    • Maximize solar and solar-ready buildings. 
    • Reduce the Energy Use Intensity (EUI) of buildings on campus. 
    • Identify opportunities to expand high efficiency energy production on campus. 
    • Implement energy storage for resiliency. 
    • Capture and store water for reuse. 

    On-Site Energy Options 

    • Vanderbilt’s central on-campus Combined Heat and Power (CHP) plant produces a portion of the electricity, all of the steam and hot water, and a portion of the chilled water consumed by the Vanderbilt community. This steam is then used for 90% of campus heating, sterilization, and 40% of campus cooling. 
    • The remaining portion of electricity consumed by Vanderbilt is purchased from the Tennessee Valley Authority (TVA) through Nashville Electric Service (NES). TVA generates power from a mix of sources including: coal–fired and natural gas power plants, nuclear power plants, hydroelectric dams, and renewable sources such as the six solar farms supported by Vanderbilt which improve the resiliency of the TVA grid. 
    • The Highland Energy Plant is designed to support the current buildings with electricity, steam, hot water, and chilled water, with the ability to anticipate and evolve to accommodate innovative technologies that have yet to be developed. 

    Vanderbilt also has: 

    • Solar-powered hot water heating systems installed in the Currey Tennis Center and the David Williams II Recreation and Wellness Center that uses solar thermal system to collect the sun’s energy to heat the water for the building. 
    • A 20kW solar photovoltaic electrical system installed on the roof of Currey Tennis Center with solar panels that generate electricity from the sun’s energy, which is fed into the Vanderbilt electricity grid. 
    • Solar-powered electronics charging stations and picnic tables. 

    A dashboard of the Currey solar panel system can be viewed online with the login: sustainvu@vanderbilt.edu and password: VU*Tennis 

    View energy consumption of campus buildings online. EnergyLogix is a web-based energy dashboard which allows the real-time monitoring of energy as well as comparing multiple buildings against each other in a user-friendly animated chart. 

  • Power Plant History

    The original Vanderbilt University Powerhouse was built in 1888 and was located in the original Mechanical Engineering Hall.

    1888 to 1925

    Boilers in the original power plant provided steam for heating of campus buildings.

    1989 to 1918

    A generator in the original power plant produce electricity for the campus. 

    1925 to 1927

    Between 1925 and 1927 a new steam plant was constructed at the current location it consisted of four boilers capable of a total of 110,000 PPH of 125 PSIG steam. 

    1961

    In 1961 Vanderbilt University purchased the high voltage substation from the local utility, and installed (2) additional 100,000 PPH boilers. 

    1980

    75,000 PPH high pressure boilers were installed along with a back-pressure turbine and "peaking" turbine. A "bag house" was installed to control particularities in boiler stack gas. 

    1993

    Three 900 tons Trane steam absorption chillers were installed in the main power plant to provide chilled water throughout campus. 

    2002

    The co-generation facility opens.

    2014

    Vanderbilt University becomes coal free and converted to on-campus co-generation, natural gas fueled power plant. 

    2015

    Two chillers were removed and replaced by 1800 ton steam turbine chiller. 

    2019

    Remaining 900 ton absorption chiller removed and replaced by 1800 ton electric chiller. 

    2021

    Vanderbilt University reached carbon neutrality, decades ahead of its initial goal. 

    2023

    Vanderbilt also opened its first solar farm through the Green Invest Program, the Vanderbilt I Solar Farm, in April of 2023.

    Vanderbilt University announces the Central Utilities Initiative.

    2025

    Opened the Highland Energy Plant increasing Vanderbilt's utility reliability and redundancy.

  • Central Utilities Initiative (CUI)

    Vanderbilt University is set to make extensive upgrades to its utilities and other infrastructure as it prepares for future campus growth. The Central Utilities Initiative, which began January 2023, will provide enhancements in support of various Vandy United projects and other future university projects.

    PROJECT DETAILS

     

    Conceptual Rendering

    Among the planned upgrades, the new initiative will enhance the resiliency and redundancy of current utility systems on campus. Capacity for utility generation also will be increased with the construction of a new power plant beginning in 2023, as well as improved distribution lines. The Highland Power Plant, which is being designed to achieve LEED certification, will be located at the recreation field on 25th Avenue South, next to the David Williams II Recreation and Wellness Center.

    Similar to the Phase I construction project in the Peabody Neighborhood in 2020, CUI will convert the original underground steam distribution system to hot water saving considerable energy and install chilled water lines, supporting the university’s sustainability goals. In alignment with Vanderbilt’s FutureVU vision, the project also will include the burying of overhead utilities, road improvements, and an enhanced pedestrian-centric environment, comparable to the transformation of the West End Neighborhood in 2019.