Rate Type
|
7/01/04 - 6/30/05
|
7/01/05 - 6/30/06
|
7/01/06 - 6/30/07
|
7/01/07 - 6/30/08
|
|
Research, on-campus
|
51.0%
|
52.0%
|
53.0%
|
53.5%
|
| Research, off-campus (Adjacent) |
28.0%
|
28.3%
|
28.3%
|
28.3%
|
| Research, off-campus (Remote) |
26.0%
|
26.0%
|
26.0%
|
26.0%
|
| Research, cost sharing |
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
|
DOD (contracts/subcontract only)
Research, on-campus
|
54.0%
|
55.0%
|
56.0%
|
56.5%
|
|
DOD (contracts/subcontract only)
Research, off-campus (Adjacent)
|
31.0%
|
31.3%
|
31.3%
|
31.3%
|
|
DOD (contracts/subcontract only)
Research, off-campus (Remote)
|
29.0%
|
29.0%
|
29.0%
|
29.0%
|
|
DOD (contracts/subcontract only)
Research, cost sharing
|
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
| Instruction |
51.0%
|
53.0%
|
53.0%
|
53.0%
|
| Other Sponsored Projects |
36.0%
|
37.0%
|
37.0%
|
37.0%
|
|
University Central Corporate Sponsors
Research, on-campus
|
54.0%
|
55.0%
|
56.0%
|
56.5%
|
University Central Corporate Sponsors
Research, off-campus (Adjacent) |
31.0%
|
31.3%
|
31.3%
|
31.3%
|
University Central Corporate Sponsors
Research, off-campus (Remote) |
29.0%
|
29.0%
|
29.0%
|
29.0%
|
University Central Corporate Sponsors
Research, cost sharing
|
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
At full rate as applicable
|
|
|
|
|
The above rates are applied
to Modified Total Direct Costs (MTDC), defined in the rate agreement as
follows:
"Modified total
direct costs, consisting of all salaries and wages, fringe benefits, materials,
supplies, services, travel and subgrants and subcontracts up to the first
$25,000 of each subgrant or subcontract (regardless of the period covered
by the subgrant or subcontract). Modified total direct costs shall exclude
equipment, capital expenditures, charges for patient care, tuition remission,
rental costs of off-site facilities, scholarships, and fellowships as
well as the portion of each subgrant and subcontract in excess of $25,000."
Off-campus (adjacent) are locations within 50 miles commuting distance
of Vanderbilt.
Off-campus (remote) are locations beyond 50 miles commuting distance of
Vanderbilt.
Equipment means an article
of nonexpendable tangible personal property having a useful life of more
than one year, and an acquisition cost of $3,000 or more per unit.
Grant-specific indirect cost
questions should be addressed to the OCGA
responsible accountant. General questions or questions related to
the development of the above rates should be forwarded to Cathy
Snyder .

|
|