Vanderbilt
to expand utility capabilities
by Lew Harris
Vanderbilt will expand its central power plant so that it can provide
steam and electricity needed to support the planned growth and renovation
of the Medical Center and University central over the next five to 10
years.
Projected growth for the campus and Medical Center is estimated at
2.7 million square feet within the next three years, with an additional
1.3 million square feet in the two years after that for a total of 4
million square feet within a five year span. Vanderbilts current steam
and electrical systems cannot accommodate such growth.
The existing central plant will be expanded by construction of a co-generation
plant, consisting of two large gas turbines, which will produce both
steam and electricity. The new facility will be constructed in the existing
power plant yard.
The present coal-based plant will continue in use, but environmental
regulations prohibit increasing its capacity. In addition, a new rock-bored
underground utility corridor will be constructed to intersect with the
Medical Centers central utility corridor.
This was a great opportunity for the central campus and the Medical
Center to work together to meet common utility needs, said Jon Gullette,
associate vice chancellor for operations. Gullette said construction
on the new project will begin in mid-October and will continue for 18
to 24 months.
The $25.2 million project, the first part of a program to expand the
University central utility infrastructure, will include the following
elements:
- Power plant expansion for added steam and electrical co-generation
capacity
- Expansion of the Universitys electrical substation by adding a
new transformer to handle the increased electrical needs
- Construction of interconnecting rock-bored tunnels to link the Central
power plant to the Medical Center utility corridors. Subterranean
drilling will be used to avoid trenching streets and other surface
excavation disruptions,
- Use of less costly Vanderbilt central utilities, rather than local
utility companies, to provide gas and electricity for a number of
existing campus buildings now purchasing from outside utilities,
- Routing natural gas from the local utility company via the new tunnels
to the central plant from the perimeter of the campus,
- Establishment of a loop system for redundant feeds to the Medical
Center for electrical and steam networks, thus increasing service
reliability.
The project will also provide redundant pathways for telecommunications
and data lines to the Medical Center and other existing buildings not
currently served. It allows the option of relocating portions of the
chilled water network, utility networks and overhead services in the
underground utility corridors.